IESO: Long-Term 2 RFP (Window 2) – October 14, 2026

Every issue in this submission lands on the same people. Ratepayers pay when a bidder sets its own number, when hydroelectric keeps a margin that solar has lost, when drought excuses a shortfall, when transmission planning makes room for stations not yet approved, and when a resource is handed a lane instead of competition. The Province’s climate assessment, the IESO’s own Annual Planning Outlook and its North of Sudbury Bulk Plan all say the water is not guaranteed. ORA asks the IESO to act on its own record.

Continue reading →


IESO: Enabling Resources Program (ERP) – Storage and Co-located Hybrid Integration Project, Phase 2 – Regulation Service Design

Howson Dam – North Maitland River, Wingham, Ontario.

The need is growing. The IESO forecasts that the minimum regulation requirement will “double to approximately 200 MW by 2030”.1 Its 2026 Annual Planning Outlook found an added need of 30 megawatts (MW) beginning in 2027, growing to as much as 110 MW by 2034.1

Batteries are arriving to meet it. The IESO expects about 3,000 MW of contracted storage to be in service by 2028.1 That is about 15 times the whole regulation requirement forecast for 2030. The IESO proposes to lift the 100 MW per minute ramp limit on batteries while they provide regulation, so that their full speed can be used to keep the grid in balance.

Continue reading →


IESO: Capacity Accreditation for IESO Procurements, engagement of 17 September 2026

Blue Heron in Waterloo, Ontario, by Leslie Bamford

ORA asks the IESO to apply the methodology it adopts to every resource class, and to publish the result for each. Hydroelectricity has been treated differently for a long time. The IESO stated its effective capacity in megawatts in 2024 and stopped. It credits hydroelectricity at roughly half to two-thirds of nameplate in its auction and has not explained how that relates to the value it will use in procurement. The one worked capacity study it has published covers battery storage and no other resource. Its public pages describe hydroelectric generation as steady and around the clock, while its own planning documents record that dependable output falls overnight and in dry periods. Ratepayers fund these contracts for 20 to 40 years,21 and they are paying for effective, dependable capacity that nobody has validated or been shown.

The IESO publishes these figures for its auction. It has not published them for procurement, and it has not published a forward-looking value for hydroelectricity at all. Nor has it shown how it derived any of them. The one-megawatt figure on the record counts pumped storage inside the hydroelectric total. The auction factor rests on five years of past output in 200 hours a season. Neither comes with a derivation a ratepayer can follow. The IESO opened this engagement on a principle of its own choosing, that its work be “Traceable”, meaning to “Allow everyone to follow the path that is being taken”.

ORA asks for that path: the inputs, the assumptions, the stations counted and the stations left out, set out so the figure can be checked by someone who does not work for the IESO. Adopting the recommendations in this submission would give hydroelectricity the same scrutiny the IESO has already applied to battery storage and would demonstrate an openness and transparency on hydroelectric generation that is long overdue.

Continue reading →


IESO: Long-Term 2 RFP – August 20, 2026

Big Falls – Victory – stopped a proposed hydroelectric project on a sacred site!

MEM knows. Its own policy paper calls hydroelectricity non-dispatchable with limited to no flexibility, records the surplus it helps create and the exports sold at or below zero, and concedes that new hydroelectric generation needs longer lead times and long-term certainty than other resources.15 The policy framework actually driving this procurement is worse. The Ministry’s June 2025 Energy for Generations makes no mention of climate change at all.31  ORA said so in its filed feedback of 12 March 2026, and says it again: an electricity plan that does not read the province’s own climate science is not planning.5 Ontario’s own Climate Change Impact Assessment, published by another ministry of the same government, rates electrical power generation infrastructure in the highest-risk category for all future time periods, and names increasing temperatures and reduced hydroelectric output as a consequence of drought.12

That assessment was not a report to one ministry. It came with a commitment from the government as a whole. The then Minister of the Environment, Conservation and Parks (MECP) wrote, in his message launching it, that “climate change requires a whole-of-government approach, and as we build Ontario, it is vital we do so in a way that will protect the well-being of current and future generations, safeguard the natural environment, ensure food and water security, enhance infrastructure and strengthen our economy.”32 Safeguard the natural environment. Ensure water security. Strengthen the economy. All three in one sentence, from this government, about this assessment.

Continue reading →


IESO: Long Lead-Time RFP: Questions and Comments

The hydro-only energy stream is not reconciled with the IESO’s own August 2025 modelling.

The LLT energy stream is restricted to new hydroelectric resources, yet the IESO’s own August 2025 Hybrid Resource Portfolio Equivalency Assessment found that wind/solar/BESS portfolios served 99.5%–99.98% of the peaky-need scenario and 99.7%–99.9% of the baseload-need scenario, and that a gas + wind/solar/BESS portfolio served 100% of load at a lower net present value than the gas-only option in seven of ten weather years. The IESO has not publicly reconciled that modelling with a decision to create an exclusive 40-year procurement lane for new hydro, together with the new transmission required to connect those projects to the grid. Citing the Directive does not discharge the IESO’s public-interest obligation to show that new hydro is necessary, least-cost and superior to lower-risk alternatives.

Nor has the IESO published any comparable analysis testing new hydro against wind, solar and BESS portfolios; the reconciliation gap is therefore wider, not narrower.

Continue reading →


IESO: Long-Term 2 RFP – June 16, 2026

ORA’s central concern is that LT2 is being used, alongside the LLT RFP and roughly 1,800 kilometres of “priority” transmission, to advance ratepayer-backed repowered and new hydropower generation as quickly as possible, without a consolidated accounting of what it will cost ratepayers, in dollars and in emissions. Cost, emissions, public health impacts, fuel price exposure, and stranded asset risk are not external to affordability and reliability; they are a huge part of it. Environmental Defence made the same point in this engagement, cautioning that procurement frameworks “should not treat these externalities as irrelevant to affordability or reliability.” ORA agrees. The IESO’s own Hybrid Resource Portfolio Equivalency Assessment found that a portfolio of wind, solar and battery energy storage systems (BESS) can meet system needs “with 99.50 to 99.98 percent of load served” in every weather year modelled, and “can provide both baseload and peak power.” Wind, solar and BESS are cheaper, cleaner and faster to deploy than hydroelectricity, and far cleaner than gas.


IESO: Regional Electricity Planning in the Northwest Region – June 11, 2026

The Chute, First Falls, Ivanhoe River – Photo by Mark Clement

During the June 11 webinar, ORA asked why wind, solar, and battery energy storage systems (BESS) could not supply some remote communities directly, rather than waiting on long transmission builds, when those resources are cheaper, cleaner, and faster to deploy. The IESO answered that this is “exactly the kind of options and considerations this planning process is meant to consider,” and confirmed that such supply resources “can certainly be done in a shorter timeframe” and “are a key aspect to helping address some of those more near-term needs” for remote communities.1 ORA welcomes that answer and writes to ensure it is carried into the demand forecast, the scenarios, and the plan that follows.

Continue reading →


IESO: Changes to the Establishment and Publication of Market Parameters – June 18, 2026

ORA’s concern is heightened by the growing influence of directives from the Minister of Energy and Mines over IESO preferences that are backed by data or studies. The April 16, 2026, Ministerial Directive instructed the IESO to procure new long lead-time hydroelectric generation, even as the Directive acknowledged that these resources are “deemed not well-suited to competing against resources with shorter development timelines and lifespans (e.g., wind, solar and inverter-based battery energy storage systems).” That instruction overrode the IESO’s own August 2025 Hybrid Resource Equivalency Assessment, which found that wind, solar, and battery energy storage systems (BESS) could serve 99.5 to 99.98 percent of load in the Peaky Need Scenario. When political direction can displace the IESO’s own expert analysis, on-the-record, Board-governed control of market parameters is not a formality. It is the safeguard that keeps ratepayer-facing decisions independent, accountable, and aligned with the public interest rather than a shifting political agenda.

Continue reading →


IESO: Regional Electricity Planning in East Lake Superior – June 4, 2026

This regional plan shows the alternative. Local needs can be met without new bulk transmission, and the IESO’s own rationale for local supply at Sault Ste. Marie, that it reduces reliance on the transmission interface, applies equally to local wind, solar, and battery storage. Resources sited near the load need only local connections, not province-spanning corridors, and can be built faster than central nuclear or major transmission lines. Some transmission will always be needed, but it is a small fraction of what is being proposed, and it is a cumulative ratepayer commitment that the public is never shown in total. Remote communities, in particular, are where local wind, solar, and battery storage should be considered first, rather than waiting for long transmission builds.

Regional transmission and generation decisions are long-lived and effectively irreversible once made. The IESO has shown in this very plan, at Chapleau and Algoma, that real needs can be met with low-cost, right-sized solutions. The Sault Ste. Marie recommendation should be held to the same standard: prove the cost honestly, keep the competition open, and do not lock ratepayers into a fossil-gas plant that the IESO’s own analysis shows is unnecessary.

Continue reading →


North Shore Link Project (Mississagi TS to Third Line TS) Draft Environmental Study Report

The Project is being advanced as a designated “priority project”, and that designation matters. Under the Ontario Energy Board Act, 1998, the Ontario Energy Board (OEB) grants leave to construct a transmission line only if the work is in the public interest, but the OEB may, by law, consider only a narrow public interest: the interests of consumers with respect to the price, reliability, and quality of electricity service. The OEB does not weigh environmental effects, which are left to the Class Environmental Assessment for Transmission Facilities (2024) (Class EA), and because the provincial government has declared this Project a “priority project”, the OEB must accept that the Project is needed; it does not test need at all. The Class EA gives the public no ability to request that the decision be elevated to a Comprehensive Environmental Assessment, and the comments received during this 30-day window are reviewed and resolved by the proponent, Hydro One Networks Inc. The result is that no independent body weighs whether this line, on this route, at this cost, and with these environmental effects, is the right choice for the public, while ratepayers and taxpayers carry the full and long-term cost.

Continue reading →