IESO: Capacity Accreditation for IESO Procurements, engagement of 17 September 2026

Blue Heron in Waterloo, Ontario, by Leslie Bamford

ORA asks the IESO to apply the methodology it adopts to every resource class, and to publish the result for each. Hydroelectricity has been treated differently for a long time. The IESO stated its effective capacity in megawatts in 2024 and stopped. It credits hydroelectricity at roughly half to two-thirds of nameplate in its auction and has not explained how that relates to the value it will use in procurement. The one worked capacity study it has published covers battery storage and no other resource. Its public pages describe hydroelectric generation as steady and around the clock, while its own planning documents record that dependable output falls overnight and in dry periods. Ratepayers fund these contracts for 20 to 40 years,21 and they are paying for effective, dependable capacity that nobody has validated or been shown.

The IESO publishes these figures for its auction. It has not published them for procurement, and it has not published a forward-looking value for hydroelectricity at all. Nor has it shown how it derived any of them. The one-megawatt figure on the record counts pumped storage inside the hydroelectric total. The auction factor rests on five years of past output in 200 hours a season. Neither comes with a derivation a ratepayer can follow. The IESO opened this engagement on a principle of its own choosing, that its work be “Traceable”, meaning to “Allow everyone to follow the path that is being taken”.

ORA asks for that path: the inputs, the assumptions, the stations counted and the stations left out, set out so the figure can be checked by someone who does not work for the IESO. Adopting the recommendations in this submission would give hydroelectricity the same scrutiny the IESO has already applied to battery storage and would demonstrate an openness and transparency on hydroelectric generation that is long overdue.

Continue reading →


IESO: 2026 Annual Planning Outlook Feedback – April 21, 2026

Vermilion River – Our grandchildren’s future with water!

ORA’s central concern with the 2026 APO is the IESO’s continuing commitment to new-build hydroelectric generation: the 1 TWh annual imputed energy stream under the Long Lead-Time (LLT) Request for Proposals (RFP), Northern Hydro Program, 20- and 40-year contracts, environmental benefits, transmissions lines, ratepayer and taxpayer impacts, and the two proposed Nine Mile Rapids and Grand Rapids hydroelectric stations in the Moose River Basin. The subsections that follow set out, on the procurement record, why this commitment is incompatible with the IESO’s own ratepayer-protection mandate.

Continue reading →


IESO: Annual Planning Outlook Demand Forecast and Demand Scenarios – November 18, 2025

The Chute, First Falls, Ivanhoe River – Photo by Mark Clement

Ontario must also stop treating hydroelectric generation as beneficial electrification or a low-carbon resource. Hydropower is not a climate solution — it is a significant and worsening source of greenhouse gas emissions. Small hydro facilities under 10 MW, with their shallow, slow-moving reservoirs, emit large quantities of methane, often comparable to the lifecycle emissions of natural gas plants. These emissions are amplified by the peaking operations required to make small-river projects economically viable: daily water-level fluctuations repeatedly wet and dry the littoral zone, accelerating decomposition and triggering intense methane release when the sediments are reflooded. As temperatures rise and nutrient-rich sediments continue to accumulate behind dams, methane production continues to increase. Far from providing climate benefits, Ontario’s small hydro fleet is fueling climate change, not mitigating it.

Relying on hydropower to “offset” a corporation’s or industry’s electricity use is carbon disinformation and a growing liability. Claiming that reservoir-based hydro is “clean” or “low-emitting” and issuing or purchasing clean energy credits based on that claim misrepresents the science and misleads the public. In ORA’s view, presenting methane-emitting hydropower as a climate solution borders on fraudulent.

The only genuinely low-carbon, scalable tools capable of supporting Beneficial Electrification are wind, solar, battery storage, and conservation.

Continue reading →


2025-2026 Annual Planning Outlook: Electricity Planning Scenarios

Lake Sturgeon stranded in a hydroelectric facility’s overflow channel.

RISKS & UNCERTAINTIES

Why is the IESO even considering procuring new hydropower when the IESO and Ontario government’s own reports provide an abundance of powerful reasons why it would be unwise? IESO’s Annual Planning Outlook (APO) is a 25-year outlook, from 2026 to 20501. It is essential to keep this in mind as you read through this submission.

Hydropower’s Climate Vulnerability:

The Report warns that “changes in Ontario’s climate are expected to continue at unprecedented rates… and it will pose indirect threats to things like water availability and water quality.”  In addition, “by the 2080s, northern Ontario, which experiences on average four extreme heat days annually, is projected to see upwards of 35 such days each year. Whereas “southern, central and eastern Ontario will average 55 to 60 such extreme heat days per year—a fourfold increase from the current annual average of about 16 days.”  This will have serious negative impacts on the intermittent and unreliable nature of hydropower generation; however, it also will have devastating effects on water quality, water quantity, aquatic life, riverine ecosystem sustainability and communities that rely on those freshwater resources.

Continue reading →


2025 Annual Planning Outlook: Demand Forecast October 30, 2024

OPG alone has 66 hydroelectric facilities in Ontario with an additional 251 associated control dams supporting those facilities, and to highlight the lack of stewardship of the OWA and OPG and their powerful influence over politicians:

  1. Ontario has 225 hydroelectric facilities and likely several hundred more associated control dams, yet there are only 2 operating fishways in all of Ontario. This is a consequential problem because dams are a major factor in the extirpation of Ontario’s Atlantic Salmon stock, one of the most important causes of significant anthropogenic mortalities and decline of Ontario’s American Eel, and a key threat to Ontario’s declining Lake Sturgeon populations.
  2. No up-front decommissioning dollars are required to be made for removal of these hydroelectric dams when they become unsafe or extended drought conditions make them a liability to our children’s future with clean water. There are zero funds in place to remove them.
  3. The OWA is responsible for amendments to the Class Environmental Assessment for Waterpower that can skip over public consultation if the proponent deems the project to be low risk. There are no low-risk hydroelectric projects, especially now that we are facing a future of rising temperatures, extreme rain events and extended droughts.
  4. The OWA is also responsible for removing public consultation for proponents converting old control dams into new hydropower generation facilities.

Public consultation and meaningful engagement actually improve a project when stakeholders have input into how the project might benefit or negatively impact on local communities. Continue reading →


IESO Engagement – 2024 Annual Planning Outlook

Manitou River

Recent hydropower shortages in BC, Alberta, Manitoba and Saskatchewan have highlighted its vulnerabilities in the face of the extremes of climate change. Hydropower is reliant upon water availability, so during the low-flow season or in times of drought, it can become intermittent and unreliable. As noted above, ongoing drought is already affecting hydropower output, and many provinces are being forced to import power or turn on the coal and natural gas facilities. Reliable hydropower does not bode well for the future.

Continue reading →