IESO: Regional Electricity Planning in East Lake Superior – June 4, 2026

This regional plan shows the alternative. Local needs can be met without new bulk transmission, and the IESO’s own rationale for local supply at Sault Ste. Marie, that it reduces reliance on the transmission interface, applies equally to local wind, solar, and battery storage. Resources sited near the load need only local connections, not province-spanning corridors, and can be built faster than central nuclear or major transmission lines. Some transmission will always be needed, but it is a small fraction of what is being proposed, and it is a cumulative ratepayer commitment that the public is never shown in total. Remote communities, in particular, are where local wind, solar, and battery storage should be considered first, rather than waiting for long transmission builds.

Regional transmission and generation decisions are long-lived and effectively irreversible once made. The IESO has shown in this very plan, at Chapleau and Algoma, that real needs can be met with low-cost, right-sized solutions. The Sault Ste. Marie recommendation should be held to the same standard: prove the cost honestly, keep the competition open, and do not lock ratepayers into a fossil-gas plant that the IESO’s own analysis shows is unnecessary.

Continue reading


ERO 025-0501 – Reg. amendments to support financing for Ontario Power Generation’s major nuclear projects

The proposal uses vague and non-binding language, asserting “no environmental impacts” to position this posting as a purely financial regulatory amendment. Additionally, it states that the SMRs and Pickering refurbishment are subject to “additional provincial and federal nuclear regulatory approvals”. However, this lacks any explicit commitment to an environmental assessment (EA) under the Ontario Environmental Assessment Act (EAA) or Canada’s Impact Assessment Act (IAA). This strategy avoids substantive public scrutiny and responsibility for environmental, climate, or health and safety assessments. This type of language circumvents the requirements under Ontario’s Environmental Bill of Rights (EBR), which mandates consideration of proposals, decisions, and events that could affect the environment, including consideration of any social or economic effects, as well as any private, public, or governmental interest factors.